In 2005 TLBP, with site landowner Jim Larsen, identified a fish passage issue on Shutters creek. For this project, we removed a 40"x20' corrugated steel culvert and replaced it with a 12'x20' steel I-beam bridge.
The outlet of the culvert
The inlet of the culvert
Engineer Harvey Wilcox and Project manager Joe Korzak surveying the site.
Work begins
Eco-blocks are placed and I-beam supports are attached
Decking is placed while engineer Harvey Wilcox inspects the bridge.
Project is completed
Three years later and the site is meeting project goals. |